Healthcare Projects

Harrison Medical Center, Bremerton, Silverdale, Port Orchard, and Belfair, WA

As Senior Project Manager for HMC's Campus Design, and Construction I worked with a multidisciplinary department team, numerous service line departments throughout the hospital, as well as senior staff for project program development, project budgeting, and project funding, along with the design, construction, and renovation of facilities at all four campuses. I was involved in developing needs assessments and feasibility studies, including space needs, spatial relationships between hospital program functionalities as well as developing initial cost estimates and project justificional statements. I was involved in the development and maintenance of design standards for campus buildings and systems, and was tasked with maintaining design and database records for all existing and new campus projects. I was involved in site-planning decisions for various projects and reviewed schematic designs for aesthetics, HMC design standards, safety codes, constructability, maintainability, and sustainability. I also managed and coordinated the efforts of the outside architects, engineers, consultants, and contractors for the development of final design documents and project construction.

In Hospital Pharmacy

Renovation and Expansion of existing Pharmacy. Project included Pre-planning, Programming, Operational Phasing, Infection Control Plan, Agency Reviews, Design, and Construction of an operational in hospital main pharmacy. Scope included upgrading from a manual distribution system to an automated, storage, dosing and distribution system, as well as upgrades to sterile storage and preparation areas. The project is complete and operational. Approximately 3,600 SF. Phased upgrades done while pharmacy continued operation 24/7.

$1 million (cost of General Construction)

$1.5 million (cost clinical equipment)

Second Linear Accelerator

Expansion from one to two Linacs in the Radiation Oncology Wing. Project included Pre-planning, Programming, Operational Phasing, Infection Control Plan, Agency Reviews, Design, and Construction of an operational Radiation Oncology Wing. Vault constructed as part of the new wing in 2004. Second Linac not anticipated for five years, but had to push it up do to volume of cases exceeding first Linac Capacity. Project require upgrade of vault for new Linac services capacity. Approximately 3,000 SF.

$350,000 (cost of General Construction)

$2.1 million (cost of clinical equipment)

Urgent Care, Imaging, & Lab

Port Orchard, WA  Two story addition to existing MOB. Providing a 24/7 Urgent Care facility, CT and X-ray Imaging Services to support the Urgent Care and Physician Offices, a full service out patient Laboratory all on the lower level, as well as upper level for future Physician Offices. Approximately 36,000 SF.

Shell and Core $6 million.

Main Level TI $1.6 million

Clinical Equipment $750K

 

Belfair, WA  Free standing single story Urgent Care (lab & Imaging) w/ shelled future Physician Office space. Approximately 10,600 SF

Shell and Core $1.5 million